324i
u
RESOLUTION No.324
A RESOLUTION ADOPTING THE SIX-YEAR STREET
PROGRAM 1964-1969 FOR THE CITY OF MOSES
LAKE,WASHINGTON
WHEREAS,the office of the City Engineer of the City of Moses Lake has
caused to be prepared a program for street improvements in the City of
Moses Lake for the six-year period from 1964 to 1969 inclusive,in
accordance with the provisions of RCW 35.77.010,and
WHEREAS,the City Council of the City of Moses Lake has held a public
hearing on the six year street program as required by RCW 35 .77.010,and
WHEREAS it is the desire of the City Council of the City of Moses Lake
to adopt the six year street program 1964-1969
NOW,THEREFORE,BE IT RESOLVED that the program entitled,"Six Year
Street Program 1964-1969,"dated February 25,1964,hereto attached
be,and the same is hereby adopted as the six year street program for
the period of 1964 to 1969 for the City of Moses Lake,Washington.
PASSED by the City Council and APPROVED by its Mayor this 15th day of
April,1964.
ATTEST:
APPROVED AS TO FORM:
(D*1y Attorney
^•-y*
City of Moses Lake
Six Year Street Program 1964-1969
1964 STREET FUND PROTECTS
1.MARINA DRIVE RAILROAD CROSSING
Description:Obtain right-of-way and construct gravel crossing.
Estimate:$2,500
2 .SEALCOATING GARDEN HEIGHTS AND MONTLAKE AREAS
Description:Continuation of sealcoating program.Includes all
streets in these areas which were paved prior to 1957.
Estimate:$10,000
3.BROADWAY (Highway 171)IMPROVEMENTS
Description:Construction of sidewalks and driveways on Broadway
from Holly Street to Lee Street.Work to be done on
Highway Department contract
Estimate LID 40%$12,000
Street Funds 18,000
Totals $30,000
1964 ARTERIAL STREET FUND PROTECTS
1.HILL AVENUE -SEALCOATING
Description:Sealcoating of Hill Avenue from Division Street to
Pioneer Way
Estimate:2<r Gas Tax Funds $2,250
Street Matching Funds 750
Total $3,000
2.ALDER STREET RAILROAD CROSSING SIGNALS
Description:Reimbursement of Chicago,Milwaukee,St.Paul and
Pacific Railroad for City's share in new signal.
Includes tie-in with existing traffic signal at
Broadway and Alder.
Estimate:a£Gas Tax Funds $4,500
Street Matching Funds 1,500
Total (City Share)$6,000
3.NELSON ROAD -HIGHWAY 17 INTERSECTION
Description:Widening the intersection and installing street
lights and paving the approaches to the intersection
of Nelson Road and Highway 17.This is a joint
project with the City,County and State Highway
Departments.City's share based on traffic volumes
on Nelson Road inside city limits is approximately 15%
Estimate:i£Gas Tax Funds $1,500
Street Matchine Funds 500
Total (City Share)$2 ,000
4.LAKESHORE DRIVE -PENINSULA DRIVE SEALCOATING
Description:
Estimate:
Expansion of 1963 program to sealcoat bituminous
surface treatment streets in sparsely settled areas
This will complete the Lower Peninsula area.
2<r Gas Tax Funds
Street Matchine Funds
Total
$3,375
1,125
$4,500
5 .PIONEER WAY -WHEELER ROAD TRAFFIC SIGNAL
Description:
Estimate:
Completion of the current project of signal install
ation at this intersection.
i<r Gas Tax Funds
Street Matching Funds
Total
$9,000
3,000
$12,000
1965 STREET FUND PROTECTS
1.PENINSULA AREA SEALCOATING
Description:
Estimate:
Completion of first phase of sealcoating paved
streets.Most streets paved prior to 1957 will
have been sealcoated.Tentatively streets are
programmed for sealcoating 10 years from the
original improvement
$7,600
1965 ARTERIAL STREET FUND PROTECTS
1.STRATFORD ROAD -VALLEY ROAD TO HIGHWAY 17
Description:
Estimate:
Paving four lanes,curbs and sidewalks in
conjunction with Highway Department improve
ment of Highway 17 (SSh 11-G)at Stratford Road
LID (40%)$24,000
H Gas Tax Funds 31,500
Street Matching Funds 4,500
Total $60,000
2 .PENINSULA DRIVE -SEALCOAT
Description:Sealcoating of Peninsula Drive from Poplar to Marigold.
Paged 1956
Estimate:5^Gas Tax Funds
Street Matchine Funds
$750
250
1,000
3.WESTERN AVENUE -RIGHT-OF-WAY ACQUISITION
Description:
Estimate:
Beginning of program to acquire right-of-way for
second lake crossing in the Peninsula area
before industry develops and cuts off the access
4$Gas Tax Funds
Street Matching Funds
$ 7,500
2,500
$10,000
4.PIONEER WAY PAVING -Part One -Proposed General Obligation Bond
Issue
Description:
Estimate:
Widen Pioneer Way to 4 lanes with parking,curbs
and 12 ft.sidewalks from Broadway and Chestnut to
Olive Ave.(60%LID)and widen to 4 lanes,no
parking,curbs,and 5 ft.sidewalks from Olive Ave.
to Highway 17 (40%LID).
LID
H Gas Tax Funds
Street Matching Funds
$132,800
127,125*
18,075
$278,000
WHEELER ROAD PAVING -Part Two -Proposed General Obligation
Bond Issue
Description:Widen Wheeler Road from Pioneer Way to Highway 17
to four lanes,no parking,curbs and sidewalk
Estimate:LID (40%)
4<r Gas Tax Fund
Street Matching Funds
Total
$ 52,400
75,750*
2,850
$131,000
*The amounts listed under i$Gas Tax Funds above will be obtained
from a General Obligation Bond Issue which would be redeemed by a portion
of the principal amount of approximately $205,000.
1966 -1969 STREET FUND PROTECTS
1.BROADWAY -LEE STREET to 1-90
Description:Extension of sidewalks,pavement and curbs to
Interstate 90.Paving,storm drainage,and curbs
would again be built by the Highway Department.
Sidewalks will be our responsibility.
Estimate:LID (40%)
Street Funds
Total
$ 14,400
21,600
$ 36,000
Note:This is the only large access street need forseeable at this time.
As this plan is revised in 1965,the program can be more accurately projected
for the period of 1966-1969 .
1966 -1969 ARTERIAL STREET FUND PROTECTS
1.WESTERN AVENUE -Right-of-way acquisition
Description:Continuation of 1965 program to obtain right-of-way
for the second lake crossing in the Peninsula area.
Estimate:i£Gas Tax Funds
Street Matching Funds
$ 15,000
5,000
$ 20,000
u
1
u
2 .PIONEER WAY -THIRD AVENUE TRAFFIC SIGNAL
Description:Traffic volumes at this intersection a year or two
ago would possibly have justified a traffic signal.
This estimate is for signal only.Physical channel
ization would very likely not be necessary.
Estimate:4£Gas Tax Funds $7,500
Street Matching Funds 2,500
$10,000
3.WHEELER ROAD -HIGHWAY 17 (SSH 11-G)TRAFFIC SIGNAL
Description:When the Highway Department recommends the
installation of a traffic signal at this intersection,
the city will have to bear a portion of the cost.
Probably 50%or more.
Estimate:4<r Gas Tax Fund $4,500
Street Matching Funds 1,500
Total (City share)$6,000
RE-CAP OF STREET AND ARTERIAL STREET PROJECTS -1964 -1969
I.1964
Project 4£Gas Tax Street LID Total
Marina Drive RR crossing -0-2,500 -0-2,500
I Garden Heights & Mont-
lake sealcoating -0-10,000 -0-10,000
Broadway -Holly to
Lee sidewalks -0-18,000 12,000 30,000
Hill Ave.Sealcoating 2,250 750 -0-3,000
Alder St.RR signals 4,500 1,500 -0-6,000
Nelson Rd.Highway 17
Intersection 1,500 500 -0-2,000
Lakeshore Dr.and
Peninsula Dr.sealcoating 3,375 1,125 -0-4,500
Pioneer Way,Wheeler Rd.
Traffic signal 9,000 3,000 -0-12,000
Totals $20,625 37,375 12,000 70,000
RE-CAP OF STREET AND ARTERIAL STREET PROTECTS -1964-1969
II.1965
Project 4£Gas Tax Street
Peninsula Area sealcoating -0-
Stratford Road widening 31,500
Peninsula Dr.sealcoat 750
Western Ave.right-of-way 7,500
Street LID Total
7,600 -0-7,600
4,500 24,000 60,000
250 -0-1,000
2,500 -0-10,000
Pioneer Way plus Wheeler
Road widening (Bond Issue
project)202,875
Totals $242,625
20,925 185,200 409,000
35,775 209,200 487,600
RE-CAP OF STREET AND ARTERIAL STREET PROTECTS -1964-1969
III.1966 -1969
4^Gas Tax Street LIDProject Total
Broadway -Lee to
1-90 -0-21,600 14,400 36,000
Western Ave.right-of-
way 15,000 5,000 -0-20,000
Pioneer Way-Third Ave.
Traffic signal 7,500 2,500 -0-10,000
Wheeler Rd.-Highway 17
Traffic signal 4,500 1,500 -0-6,000
Totals $27,000 30,000 14,400 72,000
n
n
LOCAL IMPROVEMENT DISTRICT PROTECTS
I.1964
Broadway Sidewalks $12,000
Total
II.1965
Straford Road
Pioneer Way
Wheeler Road
Total
III.1966 -1969
Penn,Fifth,Fig,Block
"D"Street,Columbia,Lakeside
Peninsula Dr.Locust,Apruce,
Sycamore,Barbara
Murphy,Bruce,Kristine,Charlotte,
Market,Buell
Nelson Road
Pine,Northshore,Knolls Vista
Total
GRAND TOTAL
STREET FUND RE-CAP
$24,000
132,800
52,400
$85,000
75,000
140,000
105,000
32,500
22,500
$12,000
$209,200
$460,000
$681,200
YEAR
1963
1964
1965
1966
1967
1968
1969
PROJECT NEEDS BUDGET NEEDS BALANCE
18,000
44,125
8,350
-0-
-0-
-0-
-0-
37,375
35,775
26,600
4,000
-0-
-0-
ARTERIAL STREET FUND RE-CAP
YEAR
1963
1964
1965
1966
1967
1968
1969
INCOME
34,500
34,500
34,500
34,500
34,500
34,500
63,500
-0-
18,250
4,000
-0-
-0-
PROJECT NEEDS
20,625
39,750
22,500
30,400*
25,900*
25,900*
♦Includes General Obligation Bond payments for Pioneer Way and
Wheeler Road improvements.Annual payment $25,900.
BALANCE
45,750
59,625
54,375
66,375
70,475
79,075
87,675